Palm Shells Can Substitute Coal To Fully Generate Power

JAKARTA – State-owned electricity company PT Perusahaan Listrik Negara (PLN), through its subsidiary PT Pembangkitan Jawa Bali (PJB), has managed to conduct a trial project of using 100 percent palm kernel shells as the substitute of coal in its coal-fired power plant (PLTU) with the capacity of 2×7 megawatt (MW) in Tembilahan area of Indragiri Hilir regency in Riau province.

PLN President Director Darmawan Prasodjo said that the use of 100% biomass of palm shells in the high co-firing (HCR) project on 15 June 2022 is the first one in Indonesia. “It also stands as an answer to the future energy in Indonesia,” he said.

He said that as part of PLN’s green booster program, the co-firing is expected to support the efforts to increase the new and renewable energy contribution to the national energy mix.

“The project of 100% biomass firing is part of PLN Group’s consistency in developing clean energy for the sake of better Indonesia in the future. As a pioneer, we hope our success will also encourage others to apply the same green project in other PLTU units,” said Darmawan.

According to him, PLN has been continually optimizing the application of co-firing up to the capacity of 1.8 giga watt (GW). It has set a target that until 2025 the biomass co-firing project will be implemented in 52 locations. So far, a total of 31 locations have seen such co-firing implementation, using 175,000 tons of the biomass, generating green power at 185 GWh and reducing CO2 at 184,000 tons.

“The co-firing program acceleration has proven that PLN is serious in supporting the government in reducing the carbon emission in the country with a view to realizing the target of carbon neutrality in 2060,” he said.

PT PJB Operation-1 Director Yossy Noval said that the pilot project of co-firing in PLTU Tembilahan is implemented gradually from 25% palm shells during the first stage on Sunday, 12 June 2022, until 100% of the biomass on Wednesday, 15 June 2022.

Their joint evaluation and technical monitoring shows that operational parameter is still normal, power load of 7 MW is kept stable and no load derating up to the maximum 100% use of biomass. Conversely, data shows that potential improvement of fuel flow and Net heat plant race (NPHR) is in quite significant percentage as the palm shells have a high calorific value.

“Environmentally, the palm shells’ content of sulfur is lower than coal so that its emission is reduced. The palm shells used for the co-firing project are derived from plantations as waste and have lower ash and carbon neutrality, which is resulted in better environment,” he said. (*)

Source: infosawit.com